Given the network plan that follows, compute the early, late, and slack times. Using any approach you wish (e.g., trial and error), develop a loading chart for resource, electrical eng

Use the attached spreadsheet template to complete the assignment.  Click on each of the tabs in the template to view each of the exercises.  

Thanks

Ch 8 Ex 4

PMT472 3.2 ASSIGNMENT: WEEK 3 EXERCISES
CH. 8 EXERCISE 4
Given the network plan that follows, compute the early, late, and slack times. Using any approach you wish (e.g., trial and error), develop a loading chart for resource, electrical engineers (EE), and resource, mechanical engineers (ME).
Start 0 1 4 5 End Legend
EE EE ME ES ID EF
2 1 6 SL Resource SL
LS DUR LF
0 2 6
EE ME
4 2
0 3 7
ME EE
3 4
Loading Schedule
EE
ME
0 1 2 3 4 5 6 7 8 9 10 11 12
What is the project duration?
(Enter response)
Assume only one of each resource exists. Given your adjusted loading schedule, compute the early, late, and slack times for your project in the resource activity schedule.
Loading Schedule (adjusted for resource constraint)
EE
ME
0 1 2 3 4 5 6 7 8 9 10 11 12
Resource Activity Schedule (with resource constraint)
ID/RES ES LS EF LF SL
1-EE
2-EE
3-ME
4-EE
5-ME
6-ME
7-EE
Which activities are now critical?
(Enter response)
What is the project duration now?
(Enter response)
Could something like this happen in real projects?
(Enter response)

Ch 9 Ex 1

PMT472 3.2 ASSIGNMENT: WEEK 3 EXERCISES
CH. 9 EXERCISE 1
Use the following information to compress one time unit per move using the least-cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity or activities were crashed and the adjusted total direct cost. Note: The correct normal project duration, critical path, and total direct cost are provided. The crash cost is how much extra it will cost to crash the activity per time unit reduced. The maximum crash time is how many time units the activity can be reduced by. E.g. Activity D can be reduced by 2 time units down to 1 time unit for a total additional cost of $120.
Activity Crash Cost (slope) Maximum Crash Time Normal Time Normal Cost
A $50 1 3 $150
B $100 1 3 $100
C $60 2 4 $200
D $60 2 3 $200
E $70 1 4 $200
F $0 0 1 $150
Crash Round 1 B D What was crashed: Activity A was reduced by 1 day (or time unit) from 3 days to 2 days.
3 3 Adjusted total direct cost: $1,050
A F The cheapest activity to reduce is A so we reduce it by its maximum reduction of one time unit to two time units. The A-C-E-F path remains critical at 11 time units and direct costs go up to $1,050 since it cost $50 to crash A.
2 1
C E
4 4
Crash Round 2 B D What was crashed: (Enter response)
Adjusted total direct cost: (Enter response)
A F
C E
Crash Round 3 B D What was crashed: (Enter response)
Adjusted total direct cost: (Enter response)
A F
C E
Crash Round 4 B D What was crashed: (Enter response)
Adjusted total direct cost: (Enter response)
A F
C E

Ch 9 Ex 2

PMT472 3.2 ASSIGNMENT: WEEK 3 EXERCISES
CH. 9 EXERCISE 2
Use the following information contained below to compress one time unit per move using the least-cost method.* Reduce the schedule until you reach the crash point of the network. For each move identify what activity or activities were crashed and the adjusted total direct cost. Note: Choose B instead of C and E (equal costs) because it is usually smarter to crash early rather than late AND one activity instead of two activities.
Activity Crash Cost (slope) Maximum Crash Time Normal Time Normal Cost
A $0 2 $150
B $100 1 3 $100
C $50 2 6 $200
D $40 1 4 $200
E $50 1 3 $200
F $0 0 1 $150
Crash Round 1 C What was crashed: (Enter response)
Adjusted total direct cost: (Enter response)
A B F
D E
Crash Round 2 C What was crashed: (Enter response)
Adjusted total direct cost: (Enter response)
A B F
D E
Crash Round 3 C What was crashed: (Enter response)

Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Ask A Question and we will direct you to our Order Page at WriteDemy. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.

Do you need an answer to this or any other questions?

About Wridemy

We are a professional paper writing website. If you have searched a question and bumped into our website just know you are in the right place to get help in your coursework. We offer HIGH QUALITY & PLAGIARISM FREE Papers.

How It Works

To make an Order you only need to click on “Order Now” and we will direct you to our Order Page. Fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Are there Discounts?

All new clients are eligible for 20% off in their first Order. Our payment method is safe and secure.

Hire a tutor today CLICK HERE to make your first order

Related Tags

Academic APA Writing College Course Discussion Management English Finance General Graduate History Information Justify Literature MLA