1. In your opinion, why it is important to identify constraints in the project schedule?

2. How should a schedule be presented to an owner? Please discuss what are the key points to be included? 

Respond to student’s discussion answer below

P U

1. A schedule constraint is a limitation added on a project schedule that affects the start or end date of an activity. Schedule constraints can take the form of fixed imposed dates for a work item, it can be used to restrict the start of an activity to occur no earlier than a specified date, rather than allowing the dates to be determined by the planning process. As soon as possible, Start no earlier than, finish no later than are some of the constrain we add in a project schedule. It is important to identity because when a constraint date is applied to a work item, that date takes precedence over dependency resolution dates during the scheduling process.

Respond

2. Many project owners prefer network diagrams when project schedule is presented to them by the contractor. The network diagram is a way to visualize the interrelationships of project activities. Network diagrams provide a graphical view of the tasks and how they relate to one another. The tasks in the network are the work packages of the WBS. All the WBS tasks must be included in the network because they must be accounted for in the schedule. Project schedules are to be provided to monitor the progress of the contractor and subcontractors relative to established schedules and to serve as status reports to the owner. The contractor administrator will discuss how the project stands with respect to the owner’s construction schedule and delivery.

Respond

D B

It is important to identify constraints in a schedule because they add elements, they may be unique to the project. As an example I worked on a high-rise building renovation project that scheduled task to subcontractors by floor completion but nothing could be done on the next floor until the asbestos abatement was complete, thus a start no earlier than constraint is appropriate.

Respond

 

A good schedule to present to owners would be a bar chart. Bar charts are simple and easy to follow the logic involved. The bar chart should include the duration, late start and finish dates without float. This way if task and the overall project is completed early the manager is looked upon favorably instead of setting an expectation to do so.

Respond

 

 

 

 

Answer

 

Discus

sion Que

s

tion

s

 

1&

2

 

1.

 

In your opinion,

 

why it is important to identify constraint

s

 

in the project schedule?

 

2.

 

How should a schedule be presented to an owner?

 

Please discuss what are the

 

key

 

points to be

included?

 

 

R

es

pon

d to

student’s

 

discussion answer

 

below

 

P U

 

1.

 

A schedule constraint is a limitation added on a project schedule that affects the start or end

date of an activity. Schedule constraints can take the form of fixed imposed dates for a work

item, it can be

used to restrict the start of an activity to occur no earlier than a specified date,

rather than allowing the dates to be determined by the planning process. As soon as possible,

Start no earlier than, finish no later than are some of the constrain we add

in a project

schedule.

It

 

is important to identity because when a constraint date is applied to a work item, that date

takes precedence over dependency resolution dates during the scheduling process.

 

 

Respond

 

2.

 

Many project owners

prefer

 

network diagrams when project

 

schedule is presented to them by

the contractor. The network diagram is a way to visualize the interrelationships of project

activities. Network diagrams provide a graphical view of the tasks and how they relate to one

another. The tasks in the network ar

e the work packages of the WBS. All the WBS tasks must be

included in the network because they must be accounted for in the schedule. Project schedules

are to be provided to monitor the progress of the contractor and subcontractors relative to

established

schedules and to serve as status reports to the owner. The contractor administrator

will discuss how the project stands with respect to the owner’s construction schedule and

delivery.

 

Respond

 

D

 

B

 

It is important to identify constraints in a schedule because they add

elements,

 

they may be unique

to the project. As an example I worked on a high

rise building renovation project that scheduled tas

k

to subcontractors by floor completion but nothing could be done on the next floor until the asbestos

abatement was complete, thus a start no earlier than constraint is appropriate.

 

Respond

 

 

A good schedule to present to owners would be a bar chart. Bar charts are simple and easy to follow the

logic involved. The bar chart should include the duration, l

ate start and finish dates without float. This

way if task and the overall project is completed early the manager is looked upon favorably instead of

setting an expectation to do so.

 

 

Respond

 

Answer Discussion Questions 1&2

1. In your opinion, why it is important to identify constraints in the project schedule?

2. How should a schedule be presented to an owner? Please discuss what are the key points to be

included?

Respond to student’s discussion answer below

P U

1. A schedule constraint is a limitation added on a project schedule that affects the start or end

date of an activity. Schedule constraints can take the form of fixed imposed dates for a work

item, it can be used to restrict the start of an activity to occur no earlier than a specified date,

rather than allowing the dates to be determined by the planning process. As soon as possible,

Start no earlier than, finish no later than are some of the constrain we add in a project schedule.

It is important to identity because when a constraint date is applied to a work item, that date

takes precedence over dependency resolution dates during the scheduling process.

Respond

2. Many project owners prefer network diagrams when project schedule is presented to them by

the contractor. The network diagram is a way to visualize the interrelationships of project

activities. Network diagrams provide a graphical view of the tasks and how they relate to one

another. The tasks in the network are the work packages of the WBS. All the WBS tasks must be

included in the network because they must be accounted for in the schedule. Project schedules

are to be provided to monitor the progress of the contractor and subcontractors relative to

established schedules and to serve as status reports to the owner. The contractor administrator

will discuss how the project stands with respect to the owner’s construction schedule and

delivery.

Respond

D B

It is important to identify constraints in a schedule because they add elements, they may be unique

to the project. As an example I worked on a high-rise building renovation project that scheduled task

to subcontractors by floor completion but nothing could be done on the next floor until the asbestos

abatement was complete, thus a start no earlier than constraint is appropriate.

Respond

 

A good schedule to present to owners would be a bar chart. Bar charts are simple and easy to follow the

logic involved. The bar chart should include the duration, late start and finish dates without float. This

way if task and the overall project is completed early the manager is looked upon favorably instead of

setting an expectation to do so.

Respond

Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Ask A Question and we will direct you to our Order Page at WriteDemy. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.

Do you need an answer to this or any other questions?

About Wridemy

We are a professional paper writing website. If you have searched a question and bumped into our website just know you are in the right place to get help in your coursework. We offer HIGH QUALITY & PLAGIARISM FREE Papers.

How It Works

To make an Order you only need to click on “Order Now” and we will direct you to our Order Page. Fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.

Are there Discounts?

All new clients are eligible for 20% off in their first Order. Our payment method is safe and secure.

Hire a tutor today CLICK HERE to make your first order

Related Tags

Academic APA Writing College Course Discussion Management English Finance General Graduate History Information Justify Literature MLA