19 Sep Answer Discussion Questions 1&2 1. In your opinion, why it is important to identify
Answer Discussion Questions 1&2
1. In your opinion, why it is important to identify constraints in the project schedule?
2. How should a schedule be presented to an owner? Please discuss what are the key points to be included?
Respond to student’s discussion answer below
P U
1. A schedule constraint is a limitation added on a project schedule that affects the start or end date of an activity. Schedule constraints can take the form of fixed imposed dates for a work item, it can be used to restrict the start of an activity to occur no earlier than a specified date, rather than allowing the dates to be determined by the planning process. As soon as possible, Start no earlier than, finish no later than are some of the constrain we add in a project schedule. It is important to identity because when a constraint date is applied to a work item, that date takes precedence over dependency resolution dates during the scheduling process.
Respond
2. Many project owners prefer network diagrams when project schedule is presented to them by the contractor. The network diagram is a way to visualize the interrelationships of project activities. Network diagrams provide a graphical view of the tasks and how they relate to one another. The tasks in the network are the work packages of the WBS. All the WBS tasks must be included in the network because they must be accounted for in the schedule. Project schedules are to be provided to monitor the progress of the contractor and subcontractors relative to established schedules and to serve as status reports to the owner. The contractor administrator will discuss how the project stands with respect to the owner’s construction schedule and delivery.
Respond
D B
It is important to identify constraints in a schedule because they add elements, they may be unique to the project. As an example I worked on a high-rise building renovation project that scheduled task to subcontractors by floor completion but nothing could be done on the next floor until the asbestos abatement was complete, thus a start no earlier than constraint is appropriate.
Respond
A good schedule to present to owners would be a bar chart. Bar charts are simple and easy to follow the logic involved. The bar chart should include the duration, late start and finish dates without float. This way if task and the overall project is completed early the manager is looked upon favorably instead of setting an expectation to do so.
Respond
Answer
Discus
sion Que
s
tion
s
1&
2
1.
In your opinion,
why it is important to identify constraint
s
in the project schedule?
2.
How should a schedule be presented to an owner?
Please discuss what are the
key
points to be
included?
R
es
pon
d to
student’s
discussion answer
below
P U
1.
A schedule constraint is a limitation added on a project schedule that affects the start or end
date of an activity. Schedule constraints can take the form of fixed imposed dates for a work
item, it can be
used to restrict the start of an activity to occur no earlier than a specified date,
rather than allowing the dates to be determined by the planning process. As soon as possible,
Start no earlier than, finish no later than are some of the constrain we add
in a project
schedule.
It
is important to identity because when a constraint date is applied to a work item, that date
takes precedence over dependency resolution dates during the scheduling process.
Respond
2.
Many project owners
prefer
network diagrams when project
schedule is presented to them by
the contractor. The network diagram is a way to visualize the interrelationships of project
activities. Network diagrams provide a graphical view of the tasks and how they relate to one
another. The tasks in the network ar
e the work packages of the WBS. All the WBS tasks must be
included in the network because they must be accounted for in the schedule. Project schedules
are to be provided to monitor the progress of the contractor and subcontractors relative to
established
schedules and to serve as status reports to the owner. The contractor administrator
will discuss how the project stands with respect to the owner’s construction schedule and
delivery.
Respond
D
B
It is important to identify constraints in a schedule because they add
elements,
they may be unique
to the project. As an example I worked on a high
–
rise building renovation project that scheduled tas
k
to subcontractors by floor completion but nothing could be done on the next floor until the asbestos
abatement was complete, thus a start no earlier than constraint is appropriate.
Respond
A good schedule to present to owners would be a bar chart. Bar charts are simple and easy to follow the
logic involved. The bar chart should include the duration, l
ate start and finish dates without float. This
way if task and the overall project is completed early the manager is looked upon favorably instead of
setting an expectation to do so.
Respond
Answer Discussion Questions 1&2
1. In your opinion, why it is important to identify constraints in the project schedule?
2. How should a schedule be presented to an owner? Please discuss what are the key points to be
included?
Respond to student’s discussion answer below
P U
1. A schedule constraint is a limitation added on a project schedule that affects the start or end
date of an activity. Schedule constraints can take the form of fixed imposed dates for a work
item, it can be used to restrict the start of an activity to occur no earlier than a specified date,
rather than allowing the dates to be determined by the planning process. As soon as possible,
Start no earlier than, finish no later than are some of the constrain we add in a project schedule.
It is important to identity because when a constraint date is applied to a work item, that date
takes precedence over dependency resolution dates during the scheduling process.
Respond
2. Many project owners prefer network diagrams when project schedule is presented to them by
the contractor. The network diagram is a way to visualize the interrelationships of project
activities. Network diagrams provide a graphical view of the tasks and how they relate to one
another. The tasks in the network are the work packages of the WBS. All the WBS tasks must be
included in the network because they must be accounted for in the schedule. Project schedules
are to be provided to monitor the progress of the contractor and subcontractors relative to
established schedules and to serve as status reports to the owner. The contractor administrator
will discuss how the project stands with respect to the owner’s construction schedule and
delivery.
Respond
D B
It is important to identify constraints in a schedule because they add elements, they may be unique
to the project. As an example I worked on a high-rise building renovation project that scheduled task
to subcontractors by floor completion but nothing could be done on the next floor until the asbestos
abatement was complete, thus a start no earlier than constraint is appropriate.
Respond
A good schedule to present to owners would be a bar chart. Bar charts are simple and easy to follow the
logic involved. The bar chart should include the duration, late start and finish dates without float. This
way if task and the overall project is completed early the manager is looked upon favorably instead of
setting an expectation to do so.
Respond
Our website has a team of professional writers who can help you write any of your homework. They will write your papers from scratch. We also have a team of editors just to make sure all papers are of HIGH QUALITY & PLAGIARISM FREE. To make an Order you only need to click Ask A Question and we will direct you to our Order Page at WriteDemy. Then fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.
Fill in all the assignment paper details that are required in the order form with the standard information being the page count, deadline, academic level and type of paper. It is advisable to have this information at hand so that you can quickly fill in the necessary information needed in the form for the essay writer to be immediately assigned to your writing project. Make payment for the custom essay order to enable us to assign a suitable writer to your order. Payments are made through Paypal on a secured billing page. Finally, sit back and relax.
About Wridemy
We are a professional paper writing website. If you have searched a question and bumped into our website just know you are in the right place to get help in your coursework. We offer HIGH QUALITY & PLAGIARISM FREE Papers.
How It Works
To make an Order you only need to click on “Order Now” and we will direct you to our Order Page. Fill Our Order Form with all your assignment instructions. Select your deadline and pay for your paper. You will get it few hours before your set deadline.
Are there Discounts?
All new clients are eligible for 20% off in their first Order. Our payment method is safe and secure.